Halvorsen Station
75.5811° S 26.2167° W · +31 m


- Site
- Brunt Ice Shelf, Antarctica
- Coordinates
- 75.5811° S 26.2167° W
- Elevation
- +31 m above sea level
- Programme
- Research station on hydraulic legs that climb with the snow.
- Year
- 2024 · complete
- Seed
- 582578538
The ice shelf moves about 400 metres a year and gains a metre of snow. A building here cannot have foundations, so Halvorsen stands on eight hydraulic legs that climb out of the drift each spring and can walk the station inland on skis when the shelf calves.
The site
Flat to the horizon in every direction. The datum itself moves, so every survey mark on the drawings carries a date.
The skin
The screen is almost closed, because the field here is almost flat. It is the quietest of the four, and the only one painted white.

01Labs on the south side: cross-laminated spruce and triple glazing. 
02Legs and skis. Each spring the legs lift the station about a metre clear of the drift.
A screen grown from the ground.
- Face
- South face
- Material
- Aluminium, painted white
- Cells
- 220
- Opening
- 10% to 26% of each cell
- Open overall
- 18%
- Seed
- 582578538
What it is made from.
Hydraulic legs, 8 no.
Lift the station 1 m a year clear of the drift
Forged and machined in Norway, tested to minus 45 °CSteel skis, 2.4 m
Foot of each leg, for towing the station inland
Fabricated in Hamburg, shipped via Cape TownAluminium panels, painted white
South screen and roof, 220 cells
Rolled in Wales, coated in a Dutch plantCross-laminated spruce
Floors and internal walls of the labs
Austrian mill, delivered in 9 flat-pack cratesMineral wool, 300 mm
Walls and floor build-up, U-value 0.11
Danish plant, vacuum-packed for transportTriple-glazed units, argon filled
Lab windows, 14 openings
Finnish glazier, packed in foam-lined timber cases
Cut through the ground.
From survey to site.
First GPS marks set on the shelf. The datum drifts 1.1 m a day, so each mark carries a timestamp.
Snow pits dug at six points. Accumulation averages 1.0 m a year, with a firm layer at 3.2 m.
Leg prototype tested in a cold chamber. One leg lifted 18 tonnes through 0.9 m in 11 minutes at minus 40 °C.
Seventy-four crates reach the shelf edge, 9 per sledge train. Haul to site takes 3 days.
Frame up on eight legs, level to 4 mm across 60 m. The shelf has moved 380 m since the first mark.
South screen hung. Labs powered on, and the first lift cycle ran for 26 hours without a fault.
Handover after the winter-over inspection. One leg reset after the first spring lift.